Stand Down Estimated Cost Dashboard

The Stand Down Estimated Cost tab on the Dashboard shows how much rental revenue stand downs are costing you, month by month, by reason, customer or equipment.

Overview

When a customer stands equipment down (for example for wet weather), you charge less for those days. This tab, on the Dashboard home screen, adds up that discount.

  • Only Completed stand downs count; cancelled ones are ignored.

  • Each stand down line's estimated cost = stand down charge days in the billing period × the stand down Discount % × the line's daily rate.

  • The estimate is worked out when the line is invoiced. Until the contract is invoiced for the stand down period, it shows as $0.

  • The cost is spread evenly over each calendar day of the stand down, then totalled by month.

  • Only owned equipment lines appear.

Before You Begin

Here's what you need to see this tab.

Requirement

Where to Find It

Equipment Stand Down Estimated Cost Dashboard permission

Security › Configuration › Permission Groups, Equipment module

Stand downs entered on rental contracts

Rental › Stand Downs or Rental › Bulk Stand Downs

A stand down needs to fall entirely inside one invoice's billing period to get an estimate. If it spans two invoices, it isn't estimated.

Using the Tab

Step 1 - Set the filters

  • Branch, Customer and Stand Down Reason.

  • Date Range - the days the stand down covers; defaults to the last 12 months including this one.

  • Group By - Reason (default), Category, Class, Model, Branch or Customer.

Click Update. Hover over a bar for the month's Total Estimated Cost.

dashboard-stand-down-estimated-cost.png
Stand Down Estimated Cost grouped by Reason - each bar is a month's estimated revenue given up to stand downs

Step 2 - Download the data

Click Download Chart Data to save Stand Down Estimated Cost.csv: one row per group and one column per month. The bookmark icon saves filters as a Saved Filter. An empty chart says "There is no data to display".

FAQs

I entered a stand down but the chart shows nothing.

The estimate is calculated when the contract is invoiced for that period, and only for Completed stand downs. Invoice the contract and the cost appears.